Bangalore
(SBC) / Hubli (UBL): The South Western Railway is unable to commence
work on two new railway lines that would have reduced railroad distance
between important cities in the State, for want of land.
The State government has not handed over
even one acre of land for the Tumkur-Rayadurg new line, via Kalyandurg
(207 km), that was announced in the 2007-08 Railway budget, and the
Tumkur-Davangere new line, via Sira (200 km), announced in the 2011-12
budget, according to sources in the South Western Railway.
The two new lines, if completed, would
reduce the distance between Bangalore and Bellary by at least 30 km and
between Bangalore and Hubli by 60 km, respectively. Now, trains from
Bangalore run via Tumkur, Birur, Chitradurga, Rayadurg (464 km) or via
Hindupur and Guntakal (358 km) to Bellary. The distance between
Bangalore and Bellary via Tumkur and Rayadurg will be 321 km, the
sources said.
Both the projects are taken up on cost
sharing basis (50:50) between the Railways and the two State
governments, while the State governments have to provide land free.
Sources said that 17 km of new line has been laid from Rayadurg in
Andhra Pradesh and 9 km would be added by this month-end. Also, work on a
major bridge across the Vedavathi in Andhra Pradesh has commenced.
However, there has been no physical progress in Karnataka, they added.
The line would also have provided rail
connectivity to backward regions in Karnataka — Koratagere, Madhugiri
and Pavagada. However, not a single acre of the 1,342 acres of land
required for the project in the State has been given to the South
Western Railway, the sources said.
Reduced distance
Similar is the case with the
Tumkur-Davangere new line. The railroad distance between the two cities
is 326 km on the circuitous route via Tumkur, Arsikere and Birur. The
proposed line via Sira, Chitradurga and Bharamasagar (along National
Highway 4) would just be 265 km.
The railroad distance between Bangalore
and Chitradurga, now 312 km, via Birur and Chikjajur, would come down to
205 km. Under this project too, no land has been given to the South
Western Railway, while the land required for the project is 2,961 acres.
South Western Railway has written letters urging the government to
expedite the process of land acquisition, the sources said. Besides
these two new lines, work on Whitefield-Kolar (52.9 km);
Marikuppam-Kuppam (23.7 km); Chikmagalur-Sakleshpur (47 km) and
Hejjala-Chamarajanagar (140 km) new lines and Hosadurga-Chikjajur line
doubling has not commenced yet for want of land, the sources added.
- Tumkur-Rayadurg line announced in 2007-08
- Tumkur-Davangere line sanctioned in 2011-12